Well.....
The housing barn is complete!
The milk barn is probably 80% complete. We still have to install 3 doors, some curbs and paint again. Then it will be ready to hook up the milk line. Oh.......we need to install the septic system to.
The creamery is probably about 80% complete as well, but it should be about 90% complete by the end of the weekend. This weekend we will install the FRP (fiberglass panels) that will line the walls. After that it will just be running the wiring and plumbing and those are both going to be surface mount so although it is a job, it won't be that bad.
We hope to be finished with the above list of things by the end of the month, but in reality it will probably be closer to the middle of February. At that point it will just be a matter of waiting for our pasteurizer to be ready and after that we will need to get our final inspections and receive our permits to begin operation.
Friday, January 14, 2011